Fairway Reconstruction to Start August 16

DODGE CITY, Kansas— Building Solutions is set to start work on the Fairway Drive Reconstruction project on Monday, August 16, at the south end of the street, near the Comanche St. intersection. The project is anticipated to be completed in five phases, each lasting three to four weeks. The project timeline may vary depending on weather and other circumstances.

During this project, Fairway Drive between Comanche St. and University Drive will be closed to thru traffic until late December. If you do not live in the construction zone, but regularly utilize Fairway Drive, please find an alternate route during this time.

Residences affected by this project will receive letters from the contractor reminding them of alternate parking and additional provisions as the project moves through the phases.