May 2, 2024

Improvements at U.S. 54/283 intersection underway in Minneola

Minneola, Kan.–The Kansas Department of Transportation has begun an intersection improvement project at the U.S. 54/283 intersection in Minneola.
 
The U.S. 54/283 intersection will be surfaced with concrete pavement and will improve traffic flow. U.S. 54 traffic will be reduced to one lane in each direction at the intersection. All lanes within the work zone area on U.S. 54 and U.S. 283 will be restricted to 12 feet. Access to all businesses within the work area will be maintained throughout the duration of the project. Motorists should expect minor delays of up to 5-10 minutes.
 
Smoky Hill LLC, of Salina, is the contractor on this $960,680.94 project, which is expected to be completed by the end of September, weather permitting.
 
For more information on this project, contact David Ubel, Construction Manager, at (620) 682-7938, or Yazmin Moreno, KDOT Southwest Region Public Affairs Manager, at (620) 260-6397.
 
The map below shows the approximate location of the project in red.